As photovoltaic power station construction expands into water‑short regions such as the northwest Gobi Desert and mountainous and hilly areas, construction challenges for PV drilling rigs in water‑free or water‑scarce formations have become increasingly prominent. Drill sticking ranks among the most frequent and hazardous accidents in water‑scarce ground conditions. In mild cases, it delays construction schedules and raises project costs. In severe cases, it can destroy drill tools, render foundation piles unusable, and even trigger safety incidents. This paper focuses on symptom identification, root‑cause diagnosis, and emergency response for drill sticking and hole collapse when working with PV drilling rigs in water‑scarce strata, offering field construction crews a systematic fault‑troubleshooting reference.
Engineering Features and Construction Challenges of Water‑Scarce Strata
| Stratum Type | Typical Characteristics | Construction Risk Level |
| Collapsible loess | Large pores, loose structure; strength drops sharply upon contact with water | High (prone to hole collapse) |
| Aeolian sand/quicksand | No cohesive force, low inter‑particle friction | Extremely high (prone to hole collapse and drill sticking) |
| Crushed stone/cobble layer | Chaotic particle distribution, large pores, no cementation | High (prone to drill sticking) |
| Weathered rock / hard rock | High hardness, well‑developed fractures | Medium‑High (prone to drill sticking) |
| Stiff plastic clay | Low moisture content, high strength | Medium |
Diagnosis and Analysis of Drill‑Sticking Failures
1. Symptom Identification of Drill Sticking
Rising rotary torque: Gradual increase in pressure readings on the power‑head rotary pressure gauge; drill pipes turn with obvious resistance
Sharp drop in penetration rate: Penetration speed suddenly falls to zero while drilling parameters remain unchanged
Abnormal noise from drill pipes: Periodic “clunk‑clunk” sounds or sharp friction noises coming from drill strings
Abnormal lifting resistance: Hydraulic system pressure for tripping out exceeds normal values by more than 30%
2. Main Causes of Drill Sticking in Water‑Scarce Strata
(1) Hole‑shrinking induced drill sticking
Certain soil types in water‑scarce formations (e.g., stiff plastic clay and expansive soil) have low natural moisture content. Yet friction and heat generated by rotating drill tools alter the state of bound water in borehole walls, making hole‑wall soil expand inward and squeeze the borehole. Once the drill bit is pulled upward, the shrunk section will tightly clamp the drill pipe or drill bit. Research indicates hole shrinkage mostly occurs when soft plastic soil swells after water exposure and narrows the borehole diameter. Repeated up‑and‑down reaming can be adopted to enlarge the borehole size.
(2) Crushed‑stone induced drill sticking
While drilling through crushed‑stone and cobble layers, large‑size rock fragments cut by the drill bit fail to get discharged out of the hole in time and get wedged between the drill bit and borehole wall. Improper drill‑bit rotating speed or overly fast tripping‑out speed may wedge rock debris into gaps between the drill bit body and the hole wall, creating a wedging‑lock effect. Special‑purpose rigs built for complex terrains such as mountain tea plantations are equipped with heavy‑duty hydraulics and matched drill bits to lower drill‑sticking risks in crushed‑stone formations.
(3) Bit bottom clogging/sticking
During dry drilling operations, drill cuttings cannot be carried away via mud circulation. Fine particles get repeatedly compacted at the bottom of the drill bit and form dense mud cakes, blocking chip‑removal passages. Negative‑pressure suction builds up beneath the drill bit, bringing about a suction‑lock effect.
(4) Hole‑wall collapse and buried drill
This represents the most dangerous scenario in loose water‑scarce strata. Sudden borehole wall collapse dumps massive soil and rock debris onto the hole bottom and buries the drill bit. Delayed handling may lead to permanent loss of drilling assemblies.
3. Emergency Response Workflow for Drill Sticking
| Stratum Type | Typical Characteristics | Construction Risk Level |
| Collapsible loess | Large pores, loose structure; strength drops sharply upon contact with water | High (prone to hole collapse) |
| Aeolian sand/quicksand | No cohesive force, low inter‑particle friction | Extremely high (prone to hole collapse and drill sticking) |
| Crushed stone/cobble layer | Chaotic particle distribution, large pores, no cementation | High (prone to drill sticking) |
| Weathered rock / hard rock | High hardness, well‑developed fractures | Medium‑High (prone to drill sticking) |
| Stiff plastic clay | Low moisture content, high strength | Medium |
Mainstream PV Drilling Rig Brands and Their Adaptability to Water‑Scarce Strata
1. Guangzhou International Technology:
Equipped with an intelligent hydraulic leveling system and multi‑mode drilling control. It automatically adjusts drilling parameters for complex water‑scarce formations including collapsible loess and crushed‑stone layers, to reduce drill‑sticking risks. Its unique dual‑variable displacement piston pump plus cartridge‑valve hydraulic system delivers strong lifting force for reliable performance against drill sticking.
2. Kerex:
Built on air‑compressor manufacturing expertise with mature DTH down‑the‑hole hammer technology. Pneumatic drilling performs well in water‑scarce hard rock formations. High‑torque hydraulics support seamless switching between auger drilling and down‑the‑hole hammer drilling, shortening borehole exposure time caused by equipment replacement.
3. UNIQUEMAC:
Track‑mounted solar‑powered drilling rig. Standard 6‑meter maximum drilling depth. Fitted with high‑strength alloy auger bits delivering 30 % higher drilling speed than ordinary bits. Proven field records in water‑scarce crushed‑stone projects in the Philippines, achieving 180‑220 completed piles per day.
4. Henan Rancheng:
Main unit power ≥56 kW with sufficient rotary torque, offering stable performance in complex strata such as till and crushed‑stone layers. Standard mast ground‑support locking system reduces hole‑wall disturbance caused by machine vibration.
5. Longye Machinery:
Specializes in steel casing wall‑protection technology requiring no mud. Low noise, low vibration, and eco‑friendly. Particularly suitable for construction in high‑water‑level compact sand layers and loose water‑scarce strata.
6. Shandong Jinxi:
Focuses on PV drilling equipment manufacturing. Accumulated abundant on‑site experience in borehole accident prevention; machine configurations address common failures such as hole collapse and hole shrinkage.
Conclusion
Drill sticking and hole collapse in water‑scarce strata essentially stem from mismatches among ground conditions, equipment performance, and construction techniques. Technological advances from domestic PV drilling rig manufacturers such as Guangzhou International Technology — including optimized hydraulic systems, intelligent controls, and multi‑mode drilling functions — provide more technical solutions for projects in water‑short regions. Still, no equipment can replace sharp on‑site judgment and standardized operation by construction personnel. Diagnosing drill sticking and hole collapse depends both on instrument readings and practical field experience. As PV projects keep expanding across arid zones, systematically summarizing failure patterns and optimizing construction methods will remain a long‑term industry task.
Contact Us – Guangzhou International Technology
📬Click the Link Contact Us to Learn More About Our Products and Deals!
🔎More Related Articles About [PV Drilling Rigs]
Emergency Response to Sand Contamination in PV Drilling Rigs Hydraulic Systems