As photovoltaic (PV) power station construction expands into tidal flats, paddy fields, lakes, and marsh plains, soft soil foundation construction has become a common challenge in PV pile foundation engineering. Soft soil has characteristics such as high moisture content, strong compressibility, low bearing capacity, and easy thixotropy. Ordinary drilling rigs in this kind of ground easily run into problems like sinking, hole deviation, hole collapse, and pile body inclination. How to efficiently and with high quality complete PV pile construction in soft soil foundations is a topic that construction units generally care about.
Main Challenges That Soft Soil Foundations Pose to PV Drilling Rig Construction
| No. | Challenge Type | Manifestation | Possible Consequence |
| 1 | Insufficient foundation bearing capacity | Machine body sinks, outriggers sink | Drilling rig tilts, hole position shifts |
| 2 | Poor hole wall stability | Hole shrinkage, hole collapse, water and mud inflow | Difficult hole formation, poor pile body quality |
| 3 | Soil thixotropy | Strength drops sharply after disturbance | Repeated settlement, difficult redrilling |
| 4 | Poor drainage conditions | Water accumulation, mud hard to solidify | Low construction efficiency, muddy site |
| 5 | Difficult pile verticality control | Uneven soft and hard layers, lateral soil squeezing | Pile inclination, difficult component installation |
Tips for Site and Equipment Preparation Before Construction
1. Site pretreatment
Lay roadbed boxes or steel plates: Lay roadbed boxes, steel plates, or crushed stone cushion layers in the areas where the drilling rig walks and works, to expand the contact area and reduce specific pressure.
Zoned flow construction: Divide the site into several work strips to avoid the drilling rig repeatedly rolling over the same area and further reducing soil strength.
Drainage first: Dig temporary drainage ditches and water collection wells in advance, and when necessary, use wellpoint dewatering to lower the groundwater level before construction.
2. Equipment selection and configuration
Small track ground pressure, good walking stability;
Sufficient power head torque reserve to adapt to rapid drilling in soft soil;
Capable of casing or guard barrel follow-up;
Mast can be finely adjusted for verticality correction.
Key Tips During the Drilling Process
1. Low rotation speed, low drilling pressure, slow footage
Control rotation speed in the medium-to-low range;
Drilling pressure should follow the principle of “light pressure, slow drilling”;
Each round of footage should not be too large, and spoil should be discharged in time.
2. Guard barrel or casing follow-up
In muddy soil and flowing plastic soft soil, construction units should use guard barrel follow-up or full casing drilling to prevent hole mouth collapse and surface water from pouring in. The guard barrel should be embedded to a certain depth below the soft soil layer into the stable soil layer and kept vertical.
3. Mud wall protection and wall protection material selection
Use bentonite mud or polymer wall protection fluid to improve hole wall stability;
Control mud specific gravity and viscosity to avoid hole collapse from being too thin or bit balling from being too thick;
In water inflow formations, plugging materials can be appropriately added.
4. Verticality control
After the drilling rig is in place, use a level to correct the chassis;
Recheck the mast verticality after drilling a certain depth;
Correct deviation in time when found, and avoid forced drilling that causes hole deviation to expand.
5. Prevent “bit burying” and “bit suction”
Control drilling speed to ensure sufficient slag discharge;
Regularly pull the bit out to clean the drill head;
When abnormal resistance is encountered, stop drilling immediately and analyze it. Do not force pressure.
Tips for Pile Formation and Subsequent Treatment
| No. | Stage | Key Tips |
| 1 | Hole completion acceptance | Check hole depth, hole diameter, and verticality. In soft soil, pay special attention to hole shrinkage |
| 2 | Rebar cage/precast pile installation | Lift and place gently to avoid hitting the hole wall |
| 3 | Concrete pouring | Pour continuously to prevent broken piles; in soft soil, slump can be appropriately increased |
| 4 | Backfilling around the pile | Use crushed stone or sand and gravel backfill to improve pile side friction |
| 5 | Site restoration | Drain and clear silt in time to prevent soil around the pile from softening |
Guangzhou International Technology PV Drilling Rigs’ Soft Foundation Construction Adaptation Approach
1. Chassis stability design: By widening the tracks and optimizing the center of gravity layout, reduce the risk of machine sinking;
2. Power and drilling matching: Aiming at the rapid slag discharge needs of soft soil, optimize the output characteristics of the power head;
3. Guard barrel follow-up matching: Support guard barrel or casing construction to reduce hole collapse;
4. Modular relocation: Adapt to the characteristics of PV projects with many sites and frequent relocation;
5. Ease of operation: Simplify verticality adjustment and outrigger control to improve soft foundation work efficiency.
Common Problems and Countermeasures
| No. | Common Problem | Cause | Countermeasure |
| 1 | Drilling rig sinking | Insufficient foundation bearing capacity | Lay roadbed boxes and steel plates to distribute load |
| 2 | Hole collapse | Unstable hole wall, improper mud | Guard barrel follow-up, adjust mud performance |
| 3 | Hole shrinkage | Soft soil thixotropy, soil squeezing | Rapid hole formation, redrilling and hole sweeping |
| 4 | Pile inclination | Uneven soft and hard layers, uneven machine body | Correct chassis, control drilling parameters |
| 5 | Bit burying | Poor slag discharge | Slow drilling, frequently pull the bit, clean the drill head |
| 6 | Soil softening around the pile | Soaking by accumulated water | Drainage, backfill reinforcement |
Summary as follows
For PV drilling rig construction in soft soil foundations, the core lies in the four words “stable, slow, protect, discharge”: the equipment must be stable, drilling must be slow, we must protect the hole wall, and slag discharge must be smooth. Before construction, do a good job in site treatment and equipment selection. During construction, control drilling parameters, strengthen wall protection, and manage verticality. After construction, backfill and drain in time. Only in this way can engineers effectively avoid problems such as hole collapse, hole deviation, and sinking. For PV projects on soft soil foundations, we recommend that construction units conduct trial piles in advance, accumulate local empirical parameters, and then promote construction over a large area, so as to achieve better economic benefits and engineering quality.
Contact Us – Guangzhou International Technology
📬Click the Link Contact Us to Learn More About Our Products and Deals!